I-35 / US 30 Flyover Progress

scottie33

Well-Known Member
Nov 25, 2006
2,710
114
63
38
Ames, Iowa
Anyone have any new insights on what is going on with these bridge piers on the I-35 to HWY 20 Fly-Over bridge?

The furthest South pier was already poured, demo'ed, and repoured. They have spent the last 3-4 weeks chipping concrete off the top of the pier and looks like they are setting up to do the same thing on the 2nd bridge pier from the South.

Also, they mobilized two (2) Manitowac 2250s, I think, a few weeks ago to lift the bridge deck beams into place but they are nowhere near being ready for them.

I can only imagine them spending about $100k/Month on crane rentals for them to just sit there.

What a catastrophe it would appear...
 

cyclone87

Well-Known Member
SuperFanatic
SuperFanatic T2
Apr 6, 2011
3,012
1,057
113
Ames, IA
They poured some or maybe all of the piers about 30" too tall is what I've heard. Now the piers have to be shortened. Not a good look for the DOT or whoever has the contract. About a month ago the project was supposed to be completed by this November. Not sure how this changes the timeline now.

Edit: Hearing it was the cast-in-place anchor bolts they had in the wrong location now and not the height.
 
Last edited:

isufbcurt

Well-Known Member
Apr 21, 2006
25,729
39,376
113
45
Newton
They poured some or maybe all of the piers about 30" too tall is what I've heard. Not a good look for the DOT or whoever has the contract. About a month ago the project was supposed to be completed by this November. Not sure how this changes the timeline now.

So they just missed the mark? lol
 
  • Funny
Reactions: cynile

ajk4st8

Well-Known Member
Mar 27, 2006
16,483
737
113
41
Ankeny
They have the wrong anchor bolts at the top of the piers and have will have to redo most of them.
 

ImJustKCClone

Ancient Argumentative and Accidental Assassin Ape
SuperFanatic
SuperFanatic T2
Jun 18, 2013
58,906
42,778
113
traipsing thru the treetops
If you look at the 1st, 2nd & 3rd piers for the exit from 35 N to 30 W while driving eastbound on 30 (with the 1st pier being the one that is actually attached to the bottom of the ramp), the 2nd pier is visibly lower than the slope of the 1st & 3rd piers, meaning the off ramp would have a dip in the middle of the curve. It's clearly visible to the naked eye.
 

CyArob

Why are you the way that you are?
Apr 22, 2011
32,469
13,389
113
MN
Sounds like they've got a great contractor out there. Didn't they already have to completely re-do one of the piers?
 

VeloClone

Well-Known Member
Jan 19, 2010
45,817
35,211
113
Brooklyn Park, MN
If you look at the 1st, 2nd & 3rd piers for the exit from 35 N to 30 W while driving eastbound on 30 (with the 1st pier being the one that is actually attached to the bottom of the ramp), the 2nd pier is visibly lower than the slope of the 1st & 3rd piers, meaning the off ramp would have a dip in the middle of the curve. It's clearly visible to the naked eye.
If you have ever installed a door you know that is exactly what wood shims are for. No big deal.




<Jimlad>
 

JP4CY

I'm Mike Jones
Staff member
SuperFanatic
SuperFanatic T2
Dec 19, 2008
64,902
78,651
113
Testifying
Sounds like they've got a great contractor out there. Didn't they already have to completely re-do one of the piers?
Yes the South one was completely demolished and redone.
 

EnhancedFujita

Well-Known Member
SuperFanatic
SuperFanatic T2
Jan 28, 2013
2,168
2,035
113
Johnston
How does this all work though? Who foots the bill for all the screw ups? I assume it's written into the contracts, but shouldn't the contracting company be footing the bill for all this, not the state?

I'd guess this is on the contractor. Unless the screw up was on the plans, which it could then fall back to the engineering company that designed it. Somehow I bet there are a bunch of lawyers involved at some point.
 
  • Winner
Reactions: Gorm

Doc

This is it Morty
Aug 6, 2006
37,437
21,963
113
Denver
This thread is bringing back memories of Professor Klaiber lecturing us on how you don't pour concrete, you place it. :) Pouring implies it's a liquid and we don't want concrete truck drivers thinking it's a liquid.
 

JSmoove

Well-Known Member
SuperFanatic
SuperFanatic T2
Jan 19, 2012
770
315
63
2611 Helser, Louden
How does this all work though? Who foots the bill for all the screw ups? I assume it's written into the contracts, but shouldn't the contracting company be footing the bill for all this, not the state?
Usually the way the contract is written is that the work isn't eligible for payment until accepted by the engineer. Now if the plans showed wrong elevations and the contractor built the bridge as specified in the plans then the state wouldn't have as much of a leg to stand on.
 

JayV

Really Big Member
SuperFanatic
SuperFanatic T2
Aug 28, 2012
787
979
93
How does this all work though? Who foots the bill for all the screw ups? I assume it's written into the contracts, but shouldn't the contracting company be footing the bill for all this, not the state?

Depends on who is at fault. Were the plans wrong? Did the something get marked wrong in the field by the surveying/staking crew? Unless it's completely obvious as to who is at fault there will be finger pointing, and likely lawyers involved to determine who pays for the mistakes and rework. May end up being a combination of factors and parties.
 

SCyclone

Well-Known Member
Mar 11, 2014
9,475
12,232
113
Fort Dodge, IA
How does this all work though? Who foots the bill for all the screw ups? I assume it's written into the contracts, but shouldn't the contracting company be footing the bill for all this, not the state?

On a job of this magnitude, the low bidder is bound to complete the project for the price he bid - unless circumstances out of his control caused delays/problems/overruns. Particularly where the government is involved, they aren't about to allow additional charges when work is done incorrectly.
 

VeloClone

Well-Known Member
Jan 19, 2010
45,817
35,211
113
Brooklyn Park, MN
Even if there are mistakes on the plans it is expected that there will be a reasonable amount of errors on plans. In my experience there have to be an extraordinary amount of errors for errors and omissions insurance to cough up for additional costs. If it was simply an error by the contractor they are responsible for R&R (remove and replace) however you can count on them submitting multiple change orders from here on out to try to recoup some of their losses.
 
  • Agree
Reactions: wxman1 and aauummm

Sousaclone

Well-Known Member
Apr 29, 2006
1,804
1,127
113
North of Seattle
How does this all work though? Who foots the bill for all the screw ups? I assume it's written into the contracts, but shouldn't the contracting company be footing the bill for all this, not the state?

Like others have said, it depends on who's mistake it is. If I (as the contractor, which I happen to be), make something 36" tall instead of 3'6" tall, then that is on me. If however the designer said 36" tall on the drawings and actually wanted it 3'6" tall, then I'm submitting a change order for extra work and delay, which the state would then be responsible for.

A lot of that stuff is normally caught by the contractor, but beam seats, or top of concrete slab elevations are hard for the contractor to back check, especially for smaller contractors that don't have tons of engineering staff supporting them.
 