I freely admit, this is not where I expected them to start the next shaft. I guess that means the perspective was throwing me off—the last one must be the main elevator shaft. Rather, the east side one.
 

Attachments

  • IMG_4253.jpeg
    IMG_4253.jpeg
    264.8 KB · Views: 58

Aclone

Well-Known Member
Dec 14, 2007
26,815
23,247
113
Des Moines, Ia.
Most recent renderings, helps put the shafts on the webcam into perspective.
 

Attachments

  • IMG_4281.jpeg
    IMG_4281.jpeg
    51 KB · Views: 114
  • IMG_4289.jpeg
    IMG_4289.jpeg
    317.8 KB · Views: 111

theshadow

Well-Known Member
Apr 19, 2006
19,945
19,586
113
Gtlt7IVXwAEH85_


AMES, Iowa – Construction begins on the South 16th Street widening project on Tuesday, June 17, weather permitting. Traffic on South 16th Street from Apple Place to west of South Riverside Drive will be maintained one lane in each direction throughout construction. The shared-use path along South 16th Street will be closed.

This marks the first phase in a two-phase project to widen South 16th Street to four lanes from University Boulevard to the Veterinary Medicine Trail. The City of Ames has contracted with Con-Struct for this project.

To accommodate the Iowa State University academic calendar and football season, the project will be constructed in two phases over two construction seasons. Substantial completion of the first phase is anticipated by Friday, Aug. 22. The second phase is scheduled for substantial completion by Friday, Aug. 21, 2026.

The project also includes the extension of storm sewer infrastructure along South 16th Street, the addition of curb and gutter, and new multi-use trail along the north and south of the street. Access to ISU Veterinary Medicine buildings will be maintained throughout the project.
 
  • Informative
Reactions: Aclone

CycloneDaddy

Well-Known Member
Sep 24, 2006
8,347
7,775
113
Johnston
Gtlt7IVXwAEH85_


AMES, Iowa – Construction begins on the South 16th Street widening project on Tuesday, June 17, weather permitting. Traffic on South 16th Street from Apple Place to west of South Riverside Drive will be maintained one lane in each direction throughout construction. The shared-use path along South 16th Street will be closed.

This marks the first phase in a two-phase project to widen South 16th Street to four lanes from University Boulevard to the Veterinary Medicine Trail. The City of Ames has contracted with Con-Struct for this project.

To accommodate the Iowa State University academic calendar and football season, the project will be constructed in two phases over two construction seasons. Substantial completion of the first phase is anticipated by Friday, Aug. 22. The second phase is scheduled for substantial completion by Friday, Aug. 21, 2026.

The project also includes the extension of storm sewer infrastructure along South 16th Street, the addition of curb and gutter, and new multi-use trail along the north and south of the street. Access to ISU Veterinary Medicine buildings will be maintained throughout the project.
Welp this will make game day a **** show this year. Hope they prove me wrong and have phase 1 done by the season opener.
 