I was wondering why that heavy crane just sat there so long, when I figured there was a good chance it was a rental.
Then I realized what today is, and that it must have been a monthly, rather than daily—if it was a rental.
Anyone can feel free to correct my wild assumptions.
Could be a rental. Even with monthly rentals I've gotten rid of equipment early. Less chance of it getting damaged while on site (even just sitting around).
Could be they were just waiting until the next job was ready for it and the GC was cool with it sitting around for a little bit.
Could be they were waiting for the heavy haul rig to be available.
Could be somebody forgot to schedule the trucks and crew to come take it apart.
Way to many variables. I've had a drilling subcontractor mobilize in and assemble a drill rig (over the course of 2 days) sit for a day, not drill a single hole with the thing, and then tear it down and send it to a different job the end of the same week it arrived. They also had the balls to audacity to try and claim it as a crane mobilization and bill us for it (which we basically told them they were idiots for and they had a less than 0% chance of getting paid for)